GB 50372-2006 炼铁机械设备工程安装验收规范 (英文版)
上QQ阅读APP看本书,新人免费读10天
设备和账号都新为新人

8.7 Commissioning of Coke Cutter

8.7.1 The commissioning of coke cutter shall meet the following requirements:

1 Allow the coke cutter to move upward/downward at a low speed,adjust the travel limit switch according to the design documents.

2 Allow the coke cutter to move upward/downward in working speed for at least 2h,the operation shall be stable,the limit switch shall operate flexibly and reliably.

3 The tip-over of coke cutter at upper bending track shall be flexible and smooth for returning,the tip-over angle shall meet the requirements in the design documents.

Check method:observe,measure and check the commissioning records.